The n-3He Experiment at SNS : Ion Chamber
Work package manager: Michael Gericke
Related Pages:
Approved Lifting Plan 11/3/2014: Ion Chamber 103014-ORNL-544-092013-Ordinary Lift Plan.pdf
Pin Map for Chamber (
pdf)
Chamber Installed:
On 11/06/2014 the target was lifted into place on the 4 point stand:

See the
Installation page for more details of the lift process.
n3He chamber CAD Model Showing Feed Throughs
|
Image of n3HeChamber Housing:
|

|

|
|
|
Frame Stack Bottom side with Teflon Shielding Over Traces
|
Top Side - no teflon shielding
|

|

|
Chamber Details:
- 2 HV Feed Thrus
- 4 Signal Feed Thrus (Shown above with 2 x 25 pin flanges Lesker Part number IFDGG251056X
- 2 Gas feed Thrus with a 90 degree elbow
Wire Planes:
- 33 wire planes
- Macor Ceramic Material
- Metallization used to apply conductive solderable traces
- 16 signal planes with 9 wires
- 17 HV planes with 8 wires
- Traces in HV frame are joined left to right for voltage distribution
- 6 guard rings are around each of the three possible three point mount positions to drain leakage current to ground before reaching signal plane
- 1.9 cm wire spacing between like wire planes (signal to signal or HV to HV)
- 0.95 cm between nearest planes (signal to HV)
- 1.9 cm spacing of wires in the planes
Signal Frame Drawing
|
HV Frame Drawing
|

|

|
Signal and HV Frame Image
 |
Left hand frame is a Signal frame. The right hand frame is a HV frame. |
Fill Gas
- He-3 to approximately 1 atmosphere
- Possible addition of nitrogen
Signal Readout
- 144 signal wires
- 4 feed throughs
- 36 signal wires per feed through
- 2 plugs per feed thru
- each plug has two cables on the back
- 10 and 15 wires on the cables
- 9 wires per cable to be used
 | Vacuum Side 25 pin Plug. PEEK with capton insulated wires. (Lesker Part No FTAK2512P)) |
|
 | Vacuum Side 25 pin Plug. PEEK with capton insulated wires. (Lesker Part No FTAK2512P)) |
|
eLog Entries:
During the testing construction and assembly of the target chamber a number entries were made in the n3He electronic log book.
The following entries in the eLog are related to the target chamber:
- 6: Wire Frame Stringing
- 7: Wire frame Stringing Progression
- 13: Leak Checking Target Chamber
- 14: Leak Checking after Weekend Bake
- 15: Leak Checking after Welding
- 16: Frame Stack Assembly pt. 1
- 17: Frame Stack Assembly pt. 2
- 18: Soldering First PCB to Frame Stack
- 19: Soldering Second Ground and First Signal PCB
- 20: Soldering PCBs
- 21: Soldering Ribbon Cable
- 22: Soldering Ribbon Cable
- 25: Survey and Alignment Frame Stack Measurements
- 26: Soldering HV PCBs
- 27: Adding Shielding to PCBs
- 28 Lifting Frame Stack into Housing
- 29: Initial HV Test
- 30: Signal Wire Verification and Layout
- 31: Sealing Flanges
Teleconference Results:
9/25/13 Teleconf
Mark:
- pieces coming out from machine shop
- chamber assembly at the end of year
- alignment under consideration
- Mark provides data for Josh to be added to the 3-D model
- Agreed an alignment meeting during DNP
- for winding Chris C. provides an optical table, winding can start after DNP
10/2/2013 Teleconf
Mark:
- working on supports to lift the wire fame assembly into the vacuum housing safely one it is assembled
- will come to ORNL Oct 27th -- Kabir will transport optical table before then
11/6/2013 Teleconf
- Chamber shipment arriving at any dat
- Mark is working towards getting ready for wiring the frames, he needs some formal procedures
he will produced some 30-40 gallons of dirty alcohol that needs to be properly disposed
- Seppo is looking at option - if it comes to that - that during run we need to replace 3He gas. How can be it done;
possibility at lab, outside but at US, or we need to ship chamber back to Canada.
- Seppo is also looking at the gas manifold requirement and do we have it
12/04/2013 Teleconf
- mark wired 27 frames out of 37, 10 to go
- also ultra sonic cleaning in process - after learning to do it properly
- PCB boards arriving in mid Jan
- after having PCB board mark can start stacking
- prio mid Jan chamber will be closed, leak checked and pumped with slight heat and then filled with pure he-4
- Tritium issue is brought up with SNS rad safety people
-
2014/08/13 Meting Presenation:
n3He-NewWireFrame r2.pdf
2014/09/12 - Magnetif Field Measurements
magData-TargetChamber - 2014_09_12.xlsx
Probing The Hadronic Weak Interaction